KU Wireless Expansion-Project Plan


For best results, please view in Mozilla Firefox or Internet Explorer 7


KU Wireless Home
Color Key Last Updated:   5/1/2008    
Not Started
Work In Progress
Completed
Wireless AP Expansion (New APs)   Survey
& Design
  Contractor Selection
and Installation
  Activation  
       
Phase1    
  Wescoe Hall              
  Fraser Hall              
  Strong Hall              
Phase 2  
  Malott Hall              
  Murphy Hall              
  Haworth Hall              
  Summerfield Hall              
Phase 3    
  Art & Design              
  Blake Hall              
  Lindley Hall              
  Robinson Health & PE Center              
Phase 4  
  Eaton Hall           May 2008  
  Snow Hall           May 2008  
  Learned Hall           May 2008  
  Budig Hall           June 2008  
  Dole HDC           May 2008  
  Smith Hall           May 2008  
  Military Science           May 2008  
  JR Pearson Hall           May 2008  
  Spencer Museum of Art           May 2008  
  Stauffer - Flint           June 2008  
  Bailey Hall           May 2008  
Phase 5  
  Marvin Studio           June 2008  
  Green Hall           June 2008  
  Marvin Hall           June 2008  
  Oldfather Studios           June 2008  
  Burt Hall           July 2008  
  Dyche Hall           July 2008  
  Spooner Hall           July 2008  
  Continuing Education Bldg.           July 2008  
  Nunemaker Hall           July 2008  
  Miscellaneous Common Areas           August 2008